Friends,
We have a situation to change the timings in the Rate Routing "Labor Time" in the Operations during mid year ( example ).
When this happens, We do NOT want to create a new Production Version OR change the STD Cost Estimate OR Product Cost Collector.
The Rep.Mfg profile is set to [ Cost Acctg: > Post Activities > Backflush using Standard Cost estimate for material ] and cannot be changed.
I know that standard SAP MFBF Activities backflush proposes values based of the Rate Routing values in the Production Version used at the Cost Estimate run and the Cost Collector. I also understand that if we re-run cost estimate and update Cost Collector, MFBF will read the current "Labor Time", but do not want to do that, because,
We want the ability to compare the MANY ACTUALS with ONE STANDARD.
Is there any way ( Via simple Enhancements/BAPI/etc ), other than Manually Changing this in MFBF to get backflush activities proposed in MFBF
based on the Latest Rate Routings "Labor Time" (Similar to discrete Production Orders Scenario) ?
Many Thanks,
MDS