Hi Dogboy,
Thank You for immediate reply.
Have you performed all PP configuration for 1007?
It means i have created order type and order type parameters, availability check,scheduling, conformation steps for the ordre type.
Master data,routing, bom creted in cewb with change number and assigned to routing in cewb.
And factory calendor assigned in work center as old plant calendor only.
Other tahn this nay steps need to consider for creation of order. anything i have missed. Please guide me.
Have you assigned a factory calendar to plant 1007?
Factory calendor is not plant specific. i think with in a client i can assign same calendor to new plant also. anywhere i have not observed the calendor as plant wise. please guide me.
Have you created a BOM for this material in 1007?
Have you created a work center in 1007? Does the work center have a factory calendar that actually exists?
The above two steps i have done.
Have you created a routing for this material in 1007, with operations in that only include work centers assigned to 1007, and assigned the routing to this material in 1007?
Yes.
Please guide me.
Regards,
Mastan.